Days Between Dates

Count the days, weeks and working days between two dates, or add days to a date to find a deadline. Advanced lets you pick your weekend, skip holidays and add times.

More options

Days between two dates

Fill in both for the exact hours and minutes.

Weekend days

Saudi Arabia, Qatar, Kuwait, Oman and Bahrain rest Friday and Saturday; the UAE moved to Saturday and Sunday in 2022.

Dates as YYYY-MM-DD, separated by commas or new lines. Holidays on a weekend day are already off.

ResultUpdates as you type—Days—Weeks and days—Years, months, days—Working days (Mon–Fri)—Weekend days—Hours—Minutes—Seconds

Add or subtract days

Do
years
months
days

Working days use the weekend and holidays chosen above.

—

How your dates are worked out

Count the calendar days, then group them into weeks and working days.

  1. 1

    Your two dates

    16 Nov 2026 →
    31 Dec 2026

  2. 2

    Count the days

    End date not counted:
    45 days

  3. 3

    Split into weeks

    45 ÷ 7 =
    6 weeks 3 days

  4. 4

    Take off weekends

    45 − 12 weekend days =
    33 working days

Read more: how days, working days, weekends and months are counted

By default the count includes the start date but not the end date, the way most people count "days until" something. From 1 January to 31 December is 364 days, or 365 if you tick the box to count the end date as well. Count both dates for things like hotel stays, leave or a contract that runs to a set date.

The formula

days = end date − start date (+ 1 to count the end date)
working days = days − weekend days − holidays on working days
hours = days × 24 (or the exact time between, with times)
new date = start date ± years and months, then ± days

Worked example

From 1 March 2026 to 1 April 2026 is 31 days (31 days in March), or 4 weeks and 3 days, or 744 hours. With a Saturday and Sunday weekend, 9 of those days are weekend days, so there are 31 − 9 = 22 working days. With a Friday and Saturday weekend there are 8 weekend days and 23 working days. Skip holidays on Friday 20 March and Monday 23 March and the Sat + Sun count drops to 20. Adding 31 days to 1 March gives 1 April again.

Working days and weekends

Working days are the days among those counted that aren't weekend days or holidays, so the end date is only included if you tick the box. Public holidays differ by country and region, so add your own in Advanced. A holiday that falls on a weekend day isn't taken off twice.

WeekendWhere it's used
Saturday + SundayMost of the world, including the UAE since January 2022
Friday + SaturdaySaudi Arabia, Qatar, Kuwait, Bahrain, Oman, Egypt, Jordan
Friday onlySix-day weeks in some Gulf jobs
Sunday onlySix-day weeks, common in parts of India and in retail

Months and years

Months don't all have the same number of days, so the years, months and days breakdown counts whole calendar months first, then the days left over. From 31 January to 1 March is 1 month and 1 day (a month ends on 28 or 29 February). When you add months, a date that doesn't exist moves to the end of the month: 31 January plus 1 month is 28 February (29 in a leap year).

Adding working days

Adding working days skips weekend days and your holidays, and doesn't count the start date. Adding 10 working days to Friday 9 October 2026 lands on Friday 23 October; with a holiday on Monday 12 October it lands on Monday 26 October.

Weekend patterns checked 9 October 2026.

Common questions

How do I count the days between two dates?

Take the start date away from the end date. From 1 March 2026 to 1 April 2026 is 31 days, or 4 weeks and 3 days. Tick the box to include the end date if you want to count both the first and last day, which adds one.

How many working days are there between two dates?

Count the days, then take away weekend days and any holidays that fall on working days. From 1 March to 1 April 2026 there are 22 working days with a Saturday and Sunday weekend, or 23 with a Friday and Saturday weekend.

Can I use a Friday and Saturday weekend?

Yes. Choose Saturday and Sunday, Friday and Saturday, Friday only or Sunday only. Friday and Saturday is used in Saudi Arabia, Qatar, Kuwait, Bahrain, Oman, Egypt and Jordan, while the UAE moved to a Saturday and Sunday weekend in January 2022.

Does the calculator know public holidays?

No, because public holidays differ by country and region. Add your own holiday dates in Advanced and they are taken off the working day count. A holiday that falls on a weekend day isn't taken off twice. Weekend patterns are set separately.

What is 31 January plus one month?

When you add months and the date doesn't exist, it moves to the end of the month. So 31 January plus 1 month is 28 February, or 29 February in a leap year. Any days are added after the years and months.

How do I add working days to a date?

Choose to add or subtract and enter the number of working days. The count skips weekend days and your holidays, and doesn't include the start date. Adding 10 working days to Friday 9 October 2026 lands on Friday 23 October.

Related calculators

Age calculatorExact age to the minute, next birthday and milestones.Hours calculatorHours between two times, weekly timesheets, overtime and pay; add or subtract times.Pregnancy due date calculatorDue date and weeks pregnant from your last period, conception, IVF transfer or a scan.Zulu (UTC) time converterConvert Zulu and local time at any airport, with military zones and date-time groups.

Made by Zulu Calculator, part of AlphaZulu LLC. Formulas are shown in full and rule figures are checked against official sources; see how we build calculators.

Embed this calculator on your site

Free to use on your website or blog. Paste this code where you want the calculator to appear. Please keep the credit link.

Days between dates by Zulu Calculator ↗